Future State Map For Current State Map
Name:
Institutional Affiliation:

Future State Map For Current State Map
Current State Analysis
The current production lead time of 23.5 days is too high and needs to be reduced by more than 50%. The current production is associated with high inventory where coils are stored and moved for only two days in a week that is Tuesday and Thursday. The products also stay for 4.5 days before they are shipped. There is a need to reduce inventory by ensuring the right amounts of raw materials and finished products are in movement. The current state map shows that the processes receive information from the production control which is a push system.
Lean manufacturing requires the information to flow the other way also referred to as a pull system. A better approach is to use the Toyota system where the production processes dictate the schedule as opposed to the production control (“Value Stream Mapping,” n.d). There is also a tremendous amount of work in progress where a single product takes. It accumulates at each machine and processes for welding and assembly. The sequencing of workflow and production is not clearly defined. Also, the change over time of 1 hour in the stamping process is too high. The overall uptime of the machine and processes also shows limited efficiency, especially for welding.
Improvements/Future State
The future state map should be able to adopt lean manufacturing strategies. The new state map will have a lower lead time, at least 7 days.

Wait! Future State Map For Current State Map paper is just an example!

The time between material release and the final product needs to be shortened. Tools like Kanban are used to reduce lead time and optimize production quantities (“Value Stream Mapping,” n.d). Customers will wait for fewer days for their finished products. This is achieved by removing steps which do not add value like travel time, work in progress inventory, reworking, material waste, and additional inspections. The machines will be grouped according to functions not according to products. Reducing the work in progress and inventory improves flow and allows the company to handle smaller quantities.

Figure 1. Future state map

Reference
Value Stream Mapping. (n.d).

Get quality help now

Top Writer

Alton Sloan

5.0 (251 reviews)

Recent reviews about this Writer

I have ordered a college case study from this company, and I’m on cloud nine! It is written in an extremely professional manner, doesn’t contain any mistakes, and is just perfect. Thank you for saving my grades!

View profile

Related Essays

Family member causing shame.

Pages: 1

(275 words)

Maths Term Paper

Pages: 1

(275 words)

Business Investments

Pages: 1

(275 words)

step1

Pages: 1

(550 words)

Military Rhetorical Essay

Pages: 1

(275 words)

Rhetorical Analysis

Pages: 1

(275 words)

Policy Proposal

Pages: 1

(275 words)

The Work of the Holy Spirit

Pages: 1

(275 words)